EVM Earned Value Method Ing. Pablo D. Argentini Grecco, MBA, PMP
Earned Value Method Costos planificados Acum $$ $50K – $40K – $30K – $20K – $10K – 0 – Costo reales Tiempo Hoy ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ La curva S da información de cómo el proyecto está avanza respecto a sus costos
Earned Value Method Real < Plan Real = Plan Real > Plan Acum $$ Costos planificados $50K – $40K – $30K – $20K – $10K – 0 – Real < Plan Costos reales Tiempo Ahora Acum $$ Costos planificados $50K – $40K – $30K – $20K – $10K – 0 – Costos reales Real = Plan Tiempo Ahora Acum $$ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ $50K – $40K – $30K – $20K – $10K – 0 – Costos reales Real > Plan Costos planificados Tiempo Ahora
Desventajas de la curva S Earned Value Method Desventajas de la curva S Sólo muestra el dinero erogado No brinda información sobre todo el proyecto Es un dato parcial Acum $$ Tiempo Plan de Costos Costo Real $50K – $40K – $30K – $20K – $10K – 0 – Ahora ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Definición de EVM El valor ganado de una tarea es su costo presupuestado por su grado de avance real Ejemplo: Una tarea fue presupuestada a un costo de $ 5.000 Está completa en un 60% El Valor ganado es $ 5.000 * 0,60 = $ 3.000 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Informe de Costo Informe de Valor Ganado Mismo Proyecto Mismo Estado Earned Value Report Costo Real Plan de costos $ Tiempo Hoy Earned Value $ Plan de costos Costo Real Tiempo Hoy Estado tarea: 80% completo ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ El proyecto gastó menos y tiene el 80% del trabajo completado A pesar que el costo real es menor al costo planificado, el valor ganado muestra que el proyecto está demorado y que gastó más de lo previsto. Diferente Informe Diferente Conclusión
¿Cuál es el estado de mi proyecto? Earned Value Method Alcance: Pintar los cuatro lados de una cerca, considerar que cada lado posee una longitud de 100 metros (en total habrá que pintar 400 metros lineales) Duración: 1 día de trabajo por cada lado Costo: 6 litros de pintura por cada lado a $4 el litro da un total de $24 por cada lado Avance el martes por la noche: Se pintaron dos lados y medio y se gastaron $70 ¿Cuál es el estado de mi proyecto? Proyecto pintar una cerca cuadrada en cuatro días de trabajo. Inicio el lunes por la mañana Hasta aquí se pintó el martes por la noche ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method DEFINICIONES FORMULAS PV (Planned Value): Valor planificado EV (Earned Value): Valor planificado de la tarea por su grado de avance real AC (Actual Cost): Costo real a la fecha BAC (Budget at Completion): Presupuesto a la finalización del proyecto EAC (Estimated at Completion): Costo a erogar bajo condiciones actuales ETC (Estimated to Complete): Costo pendiente de erogación bajo condiciones actuales VAC (Variance at Completion): Varianza de costo a la finalización bajo condiciones actuales FORMULAS CV = EV – AC (Cost Variance) SV = EV – PV (Schedule Variance) CPI = EV / AC (Cost Performance Index) SPI = EV / PV (Schedule Performance Index) EAC = BAC / CPI (Estimated at Completion) ETC = EAC - AC (Estimate to Complete) VAC = BAC – EAC (Variance at Completion) ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Proyecto Alcance: 400 metros Duración: 1 día de trabajo por lado Costo por lado: 6 litros de pintura, $4 por litro = $24 Avance el martes por la noche: Se pintaron dos lados y medio y se gastaron $70 PV = EV = AC = BAC = SV = EV - PV = CV = EV - AC = SPI = EV / PV = CPI = EV / AC = EAC = AC + (BAC - EV) / CPI = ETC = EAC – AC = VAC = BAC – EAC = Proyecto pintar una cerca cuadrada en cuatro días de trabajo. Inicio el lunes por la mañana Hasta aquí se pintó el martes por la noche ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Proyecto Alcance: 400 metros Duración: 1 día de trabajo por lado Costo por lado: 6 litros de pintura, $4 por litro = $24 Avance el martes por la noche: Se pintaron dos lados y medio y se gastaron $70 PV = 2 * $24 = $48 EV = (100% * $24) + (100% * $24) + (50% * $24) = $60 AC = $70 BAC = $24 * 4 = $96 SV = EV - PV = $60 - $48 = $12 CV = EV - AC = $60 - $70 = -$10 SPI = EV / PV = $60 / $48 = 1,25 CPI = EV / AC = $60 / $70 = 0,85 EAC = AC + (BAC - EV) / CPI = $70 + ($96 - $60) / 0,85 = $112 ETC = EAC – AC = $112 – $70 = $42 VAC = BAC – EAC = $96 – $112 = -$16 Proyecto pintar una cerca cuadrada en cuatro días de trabajo. Inicio el lunes por la mañana Hasta aquí se pintó el martes por la noche ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Si medimos al cierre de la 3ª semana: PV = $5.100 CV = EV – AC = SV = EV – PV = CPI = EV / AC = SPI = EV / PV = EAC = BAC / CPI = ETC = EAC - AC = VAC = BAC – EAC = PV = $5.100 EV = $4.550 AC = $4.250 BAC = $6.000 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Si medimos al cierre de la 3ª semana: PV = $5.100 CV = EV – AC = $300 SV = EV – PV = -$550 CPI = EV / AC = $4.550 / $4.250 = 1.07 SPI = EV / PV = $4550 / $5.100 = 0.89 EAC = BAC / CPI = $6.000 / 1.07 = $5.607 ETC = EAC - AC = $5.607 – $4.250 = $1.357 VAC = BAC – EAC = $6.000 – $5.607 = $393 PV = $5.100 EV = $4.550 AC = $4.250 BAC = $6.000 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method VIEJA TERMINOLOGIA NUEVA TERMINOLOGIA BCWS – Budgeted Cost of Work Scheduled BCWP – Budgeted Cost of Work Performed ACWP – Actual Cost of Work Performed NUEVA TERMINOLOGIA PV – Planned Value EV – Earned Value AC – Actual Cost ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method $ 6.000 $ 5.000 PV $ 2.500 AC EV Hoy Al cierre $ Estimado al completar (EAC) $ $ 6.000 Presupuesto al completar (BAC) Presupuesto del trabajo remanente $ 5.000 Estimado para completar (ETC) PV $ 2.500 AC Variación de costo (CV) EV Variación de cronograma (SV) ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- Tiempo Hoy Al cierre
Varianza de Costo y Cronograma. Ejercicio Earned Value Method Varianza de Costo y Cronograma. Ejercicio Acum $ Plan de costos $50K – $40K – $30K – $20K – $10K – 0 – Varianza de costo ( + / - ) Varianza de cronograma ( + / - ) Valor Ganado Costos Reales Tiempo Hoy Acum $ Plan de costos $50K – $40K – $30K – $20K – $10K – 0 – Costos Reales Varianza de costo ( + / - ) Varianza de cronograma ( + / - ) Valor Ganado Tiempo Hoy ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ Acum $ Valor Ganado $50K – $40K – $30K – $20K – $10K – 0 – Costos Reales Varianza de costo ( + / - ) Varianza de cronograma ( + / - ) Plan de costos Tiempo Hoy
Earned Value Method La varianza de costo es positiva. Acum $$ Plan de costos La varianza de costo es positiva. Está gastando menos de lo planeado. La varianza del cronograma es negativa. Está atrasado. $50K – $40K – $30K – $20K – $10K – 0 – Valor Ganado Costos Reales Tiempo Hoy Acum $$ Plan de costos La varianza de costo es negativa. Está gastando más de lo planeado. La varianza del cronograma es negativa. Está produciendo menos trabajo que el planeado. Está atrasado. $50K – $40K – $30K – $20K – $10K – 0 – Costos Reales Valor Ganado Tiempo Hoy Acum $$ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ Valor Ganado La varianza de costo es positiva. Está gastando menos de lo planeado. La varianza del cronograma es positiva. Está adelantado. $50K – $40K – $30K – $20K – $10K – 0 – Costos Reales Plan de costos Tiempo Hoy
Earned Value Method CPI y SPI Evaluación CPI CPI SPI 1.5 El PM dice que el costo estará dentro del presupuesto 1.4 1.3 1.2 1.1 1.0 Tiempo 0.9 0.8 0.7 CPI 0.6 0.5 1.5 El PM dice que el costo estará dentro del presupuesto 1.4 1.3 1.2 CPI 1.1 1.0 Tiempo 0.9 0.8 0.7 0.6 0.5 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ 1.5 SPI El PM dice que terminará en fecha 1.4 1.3 1.2 1.1 1.0 Tiempo 0.9 0.8 0.7 0.6 0.5
Earned Value Method El CPI < 1 Tiempo 1.5 1.4 1.3 1.2 1.1 1.0 0.9 0.8 0.7 0.6 0.5 El PM dice que el costo estará dentro del presupuesto SPI El CPI < 1 El proyecto más de un 20% de lo planificado y permanece en esa tendencia. CPI > 1 El proyecto está dentro del presupuesto y debería terminar entre un 10% al 20% por debajo del presupuesto. La productividad fue más alta que la planeada. El PM dice que terminará en fecha ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ SPI > 1 El proyecto está adelantado. El trabajo se está haciendo un 20% más rápido de lo planeado.
Earned Value Method Si EV = 350, AC = 400, PV = 325 ¿cuál es la Variación de Costo (CV)? A. 350 B. -75 C. 400 D. -50 Un CPI (Cost Performance Index) de 0,89 significa A. Que en este momento esperamos que el proyecto cueste 89% más de lo planificado. B. Que cuando se complete el proyecto habremos gastado 89% más de los planificado. C. Que el proyecto está progresando a solamente 89% de lo planificado. D. Que el proyecto está obteniendo solamente 89 centavos por cada peso invertido. Un SPI (Schedule Performance Index) de 0,76 significa A. Que estás pasado del presupuesto B. Que estás adelantado en el tiempo C. Que estás progresando a solamente 76% del ritmo planificado originalmente D. Que estás progresando a solamente 24% del ritmo planificado originalmente ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Usando la tabla de abajo, el schedule performance index (SPI) para el elemento P del WBS es: A. 1,10 B. 0,90 C. 0,956 D. 1,15 Elemento del WBS PV EV AC P $1.000 $1.100 $1.150 Q $2.000 $1.800 $2.100 R $1.200 $1.050 S $1.900 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------
Earned Value Method Usando la tabla ¿qué elemento está sobre el presupuesto y atrasado en el tiempo? A. Elemento P B. Elemento Q C. Elemento R D. Elemento S Usando la tabla ¿qué elemento tiene un Cost Variance de $150? Elemento del WBS PV EV AC P $1.000 $1.100 $1.150 Q $2.000 $1.800 $2.100 R $1.200 $1.050 S $1.900 ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------